Public data, updated November 19, 2026 Sources: NHTSA, EPA, AFDC

Fleet ยท Updated November 19, 2026

Fleet charging load calculator

Enter how many vehicles charge at your depot, how far they drive, how long they are plugged in and what your chargers can deliver. The calculator tells you how much energy you need per night, whether your ports can deliver it in the time available, and what site load that means. It has no built-in prices and no default values. Every number is yours, except one optional EPA energy figure that you choose to load.

What you enter

Every field starts empty. The only value the page can fill in is an EPA energy figure, and only if you choose to load one. Enter either your own energy use per mile or an EPA value: one of the two is needed. If you fill both, the EPA value is used and the loss factor is ignored. Vehicles and ports are whole numbers.

Field Unit
Vehicles that charge at the depot each night vehicles
Miles driven per vehicle per day miles
Energy use per mile kWh per mile
EPA label energy use for a chosen trim (optional prefill) kWh per 100 miles
Charging loss factor for your own energy figure (blank means none; ignored when the EPA value is used, because EPA includes charging losses) multiplier, 1 or more
Hours the vehicles are parked and plugged in hours
Number of charging ports ports
Rated output per port kW
Most power the vehicle accepts kW

How it works

  1. Energy per vehicle per day = miles per day x kWh per mile. If you typed your own kWh per mile, did not load an EPA value, and entered a charging loss factor, multiply by that factor.
  2. Energy for the site per night = vehicles x energy per vehicle.
  3. Effective kW per port = the smaller of the port's rated kW and the vehicle's accepted kW.
  4. Hours to charge one vehicle = energy per vehicle / effective kW per port.
  5. Charging rounds = vehicles divided by ports, rounded up.
  6. Hours needed = rounds x hours to charge one vehicle. It fits if this is no more than the hours parked, with both compared to two decimal places.
  7. Lowest possible average site load = site energy / hours parked.
  8. Peak site load if every port starts together = the smaller of vehicles and ports, times effective kW per port.

About the optional EPA prefill

EPA lists energy use in kWh per 100 miles in the "combE" field of its vehicle data file. It defines the field as combined electricity consumption in kWh/100 miles. Divide by 100 to get kWh per mile. The file (last modified Wed, 04 Nov 2026 14:31:23 GMT) has 50,647 rows, and 1,684 of them have fuelType Electricity, 1,393 of those for model year 2022 or later. fueleconomy.gov says its MPGe and kWh/100 mile estimates for plug-in vehicles include losses that occur during charging, so the calculator ignores the loss factor when you use an EPA value. EPA values reflect label test results, and your fleet may differ (EPA, https://www.fueleconomy.gov/feg/download.shtml, retrieved 2026-11-19).

For reference, the EPA file lists the 2022 Chevrolet Bolt EV (vehicle id 43955) with combE 28.1083, charge240 of 7.5 hours (time to charge at 240 V) and a range of 259 miles. This is shown as a data point from the file, not as a suggested input.

What this does not do

  • It does not calculate demand charges or utility tariffs.
  • It assumes constant power at each port. It does not model charge-curve taper.
  • Peak site load uses each port's effective kW (the smaller of its rated kW and the vehicle's accepted kW) and ignores any site power cap or load management.

No worked example

This page shows no example run. Fleet size, daily miles and dwell time vary by operator, and we have no cited public figure for them, so any example would be invented.

Related

Sources